ADR tank special provision TE12

Organic peroxide tanks: insulation, temperature sensors, spring-loaded safety valves and emergency relief sized for one hour of full fire engulfment.

Tanks need thermal insulation meeting 6.8.3.2.14, full insulation where the SADT is 55 °C or less or the tank is aluminium, white or bright-metal outer surfaces, combustible-free insulation and temperature sensors. Safety valves and emergency pressure-relief devices are required, vacuum-relief devices are optional and fusible elements are banned in the shell body. Spring-loaded safety valves must stop significant pressure build-up from decomposition products and vapours given off at 50 °C, sized and set from the TA2 test results, and set so liquid cannot escape if the tank overturns. Emergency-relief devices, spring-loaded or frangible, must vent everything produced over at least one hour of complete fire engulfment, calculated with the formula given. Their set pressure is above the safety valves' and based on the TA2 tests, and the tank pressure must never exceed the test pressure. With complete cladding, sizing assumes insulation is lost from 1 % of the surface. Vacuum-relief devices and spring-loaded safety valves need flame arresters unless the cargo and its decomposition products are non-combustible, allowing for the capacity the arrester takes away.

Limits
ValueApplies when
55 °CSADT at or below which the shell must be completely insulated
50 °Ctemperature of decomposition products and vapours the safety valves must handle
1 hourminimum duration of complete fire engulfment for emergency-relief sizing
70961 coefficientq = 70961 × F × A^0.82, heat absorption in W
0.82 exponentexponent applied to the wetted area A in m²
1 %share of surface area assumed to lose insulation for fully clad tanks

Conditions

equipmentthermal insulation, sun shield or white/bright-metal finish, temperature sensing devices, spring-loaded safety valves, emergency pressure-relief devices, flame arresters where required

Note. The insulation-factor formula reads: F = 1 for non-insulated tanks, and for insulated tanks F is printed as U (923 - TPO) over 47032, with U = K/L. Symbols checked against a UTF-8 text extraction of the page. The text continues onto page 536. For a worked sizing example the NOTE cites the Manual of Tests and Criteria, Appendix 5.

Refers to: 6.8.3.2.14; special provision TA2; Manual of Tests and Criteria, Appendix 5.

Carried by 4 Table A entries

UN 3109 · UN 3110 · UN 3119 · UN 3120

Source: ADR 2025 (ECE/TRANS/352), Volume II, section 6.8.4 (b), TE12, page 535.

Paraphrase in FreightUtils' own words, not the official text. Not yet reviewed.

ADR 2027 amendments (accepted, applying from 1 January 2027) are not yet reflected on this page.