ADR tank special provision TT3
Periodic inspections at most every eight years with an instrument thickness check; leakproofness test and check at most every four years.
Departing from 6.8.2.4.2, the periodic inspection is due no later than every eight years and must include measuring wall thickness with suitable instruments. For these tanks, the leakproofness test and check of 6.8.2.4.3 is due no later than every four years.
| Value | Applies when |
|---|---|
| 8 years | maximum interval between periodic inspections |
| 4 years | maximum interval for the 6.8.2.4.3 leakproofness test and check |
Refers to: 6.8.2.4.2; 6.8.2.4.3.
Carried by 16 Table A entries
UN 1389 · UN 1391 · UN 1392 · UN 1407 · UN 1415 · UN 1420 · UN 1421 · UN 1422 · UN 1423 · UN 1428 · UN 2257 · UN 3401 · UN 3402 · UN 3403 · UN 3404 · UN 3482
Source: ADR 2025 (ECE/TRANS/352), Volume II, section 6.8.4 (d), TT3, page 537.
Paraphrase in FreightUtils' own words, not the official text. Not yet reviewed.
ADR 2027 amendments (accepted, applying from 1 January 2027) are not yet reflected on this page.